    The value case for an AI project: baseline, calculation, sensitivity and the non-AI alternative

    How to build the document that decides whether a project gets funded: baseline measurement method, expected value formula, three-year cost, sensitivity analysis and stop thresholds.

    ZeroFive.AI October 13, 2026Updated on October 14, 2026 12 min

    In short. A value case is defensible when it holds four things an outsider to its drafting can verify: a baseline measured over a stated period, an expected value calculation with every assumption spelled out, the three-year total cost including ongoing oversight, and the non-AI alternative costed with the same arithmetic and ruled out in writing. Without that last item the comparison stays between doing the project and doing nothing, which is a comparison that always wins.

    This article sets out how the document gets built, with the measurement method, the formulas, a full worked example and the calculation errors that recur in the business cases we review.

    The eight elements of a defensible value case

    ElementWhat has to be thereWho provides it
    Measured problemThe starting number, with period and data sourceProcess owner
    BaselineVolume, time per unit, rework rateWhoever runs the process
    Non-AI alternativeThe simplest option, costed with the same methodWhoever proposes
    AI optionScope, data, integrations, share of cases coveredWhoever designs
    Expected valueFormula, assumptions, a range rather than a single numberProposer, with finance
    Three-year total costBuild, consumption, integration, oversight, exitDesigner, with IT
    Risk and classificationWhere the system lands and which obligations followRisk or compliance function
    Stop criteriaNumeric thresholds and a review dateWhoever signs

    The right-hand column is the one most often missing, and its absence explains why many documents don't survive the first hard question. A number without an owner is a number nobody will defend in committee.

    The baseline, before any promise

    The baseline is the measure of the process as it stands today, and it has to be collected before the project is announced, because the announcement changes the behaviour of the people doing that work.

    Three quantities and a period are needed. Volume, as the number of units handled in the chosen interval. Time per unit, measured on a sample rather than recalled by the manager. Rework rate, the share of units that come back or need a second pass.

    The observation period deserves care. Four weeks is the minimum for a process with weekly seasonality, while a process with monthly peaks needs at least two full cycles. A baseline taken during a peak inflates the expected value, one taken in a quiet stretch depresses it.

    On sampling, a practical rule: thirty units timed by two different people give a more defensible measure than an internal survey of a hundred, because perceived time spent is systematically biased upward for unpleasant tasks.

    Finally, record who collected the data and with what instrument. A baseline pulled from system logs carries different evidentiary weight than one gathered on a spreadsheet, and that difference matters when the final result is challenged.

    How expected value is calculated

    Gross expected value comes from volume times time saved per unit times the fully loaded hourly cost of the function involved. Fully loaded means including contributions and indirect costs, because using gross pay understates the saving materially in most Italian organisations.

    Three reduction factors then apply to that number, and each has to be declared.

    The share of cases the system covers, because no solution handles the entire flow. Residual verification time, the minutes a person still spends checking the output, high in the early months and falling as trust builds. The adoption rate, which in the first year rarely reaches the theoretical potential, because habit around the previous process holds.

    The result belongs in a range. A value case declaring an annual saving of 56,000 euro is less credible than one declaring a range between 38,000 and 61,000 with the assumptions producing each end, because the second shows the unfavourable scenario was considered.

    One distinction finance will raise anyway is worth addressing upfront. Freed time becomes a saving only if it converts into lower costs or into additional capacity actually sold. In staff functions, where nobody will be replaced, the benefit belongs in the document as recovered capacity, tied to what those hours will do in place of the eliminated work.

    Three-year total cost

    LineNatureEstimating note
    Design and buildOne-offIncludes data preparation, the most underestimated line
    Integration with existing systemsOne-offGrows with the number of downstream systems receiving the output
    Model consumption or licencesRecurringSize it on worst-case behaviour rather than the average
    Internal validation timeRecurring, decreasingHigh in the first three months, budget it anyway
    Oversight and maintenanceRecurringBetween 10 and 20% of build cost per year
    Documentation and compliance workVariableDepends on the system's classification
    Exit costContingentReturn to the manual process, data migration, reverse training

    The three-year horizon makes the weight of the recurring lines visible. A project costing 45,000 euro to build and 18,000 a year to run carries a three-year cost of 99,000, and comparing the annual benefit against the initial 45,000 alone produces a decision taken on a third of the numbers.

    A worked example

    The figures below are illustrative and serve to show the mechanics of the calculation.

    A services company handles 1,400 case files a month. The completeness check takes 11 minutes per file on average, around 257 hours a month. At a fully loaded hourly cost of 32 euro, that process is worth roughly 8,200 euro a month, a little under 99,000 a year.

    The hypothesis is a system that checks completeness and flags anomalies. The share of standard, therefore treatable, files is estimated at 70%. Residual verification time on the output is 2 minutes per treated file. The first-year calculation comes out as follows.

    LineValue
    Gross hours freed, 70% of 257180 hours/month
    Residual verification, 980 files at 2 minutes33 hours/month
    Net hours freed147 hours/month
    Gross annual value, 147 hours at 32 euro over 12 monthsabout 56,400 euro
    Correction for 70% adoption in year oneabout 39,500 euro
    Recurring costs, year one18,000 euro
    Operating margin, year oneabout 21,500 euro
    One-off build45,000 euro

    Cumulative cash stays negative by around 23,500 euro at the end of year one. With adoption at full rate, year two generates a margin near 33,000 euro, putting breakeven around the twentieth month from start.

    Sensitivity analysis is what separates a serious document from a hopeful one. If the share of treatable files drops from 70 to 50 per cent, the annual margin at full rate falls below 10,000 euro and breakeven passes four years, meaning the project should not be funded. The value case has to state that threshold, because it names the assumption the pilot must test first.

    Which framework does your company actually need?

    AI Rating measures maturity across the four areas of the model and shows where to start, with priorities and estimated effort.

    Start your AI Rating

    The non-AI alternative, costed with the same arithmetic

    The alternative deserves the same method rather than a single dismissive line. In most processes two cheaper options exist before the model.

    OptionInterventionIndicative costShare of problem solved
    A, processMandatory fields upstream, authorisation thresholds, formsLow, weeksOften between 30 and 50%
    B, deterministic rulesAutomated checks on known conditions, no modelMedium, 4-10 weeksBetween 40 and 70% on standard cases
    C, AI systemInterpretation of unstructured inputHighThe residue A and B don't cover

    In the projects we assess, option B covers a substantial part of what the proposer attributed to AI, at lower build and oversight cost and with predictable behaviour. That doesn't cancel option C, it resizes it: the residual value of AI belongs on the delta against B, not against the manual starting process.

    Writing the alternative down doesn't mean choosing it. It means stating why it was ruled out, and that sentence is the part of the document the committee will read most closely.

    Regulatory risk in the arithmetic

    The system's classification carries an economic effect that has to be estimated, because a system falling under Annex III of the AI Act brings risk assessment, technical documentation, structured human oversight, event logging and, for some deployers, a fundamental rights impact assessment.

    In the cases we follow, that package adds a significant share to project cost and a recurring maintenance commitment, with the burden concentrated in control functions rather than the technical team. A value case ignoring this line understates cost precisely in the most sensitive use cases.

    The practical consequence concerns the order of work. Classification belongs before the economic calculation, because it changes the denominator, rather than after approval, when the budget has already been committed.

    Stop criteria written as thresholds

    A useful stop criterion is a number with a date. Wording like review progress after a few months stops nothing, because it leaves the decision to the discretion of whoever has an interest in continuing.

    A defensible formulation reads like this: if at week twelve the share of files handled without human intervention stays below 55 per cent, or the output correction rate exceeds 20 per cent, the project stops and option B is reconsidered.

    Three elements are needed. The metric, already measured in the baseline. The threshold, derived from sensitivity analysis rather than chosen by feel. The date, fixed in advance and put in the calendar alongside the person with the authority to stop the project.

    The calculation errors that recur

    The first is counting the same time twice. When several initiatives each claim to free hours from the same function, the sum of benefits exceeds the hours actually available there, and the portfolio promises a saving that is arithmetically impossible.

    The second is treating as a saving time that stays in the company. If nobody is reallocated and no additional volume is absorbed, the benefit is latent capacity, and declaring it as cost reduction exposes the project to a review it won't survive.

    The third is ignoring verification time. A system handling seventy per cent of cases while forcing a full recheck produces a net saving close to zero, and that check belongs in the pilot measurement rather than in a desk estimate.

    The fourth is using the pay rate instead of the fully loaded hourly cost, which understates the benefit and, perversely, makes the project easier to reject.

    The fifth is discounting internal time to zero during the project. The hours of people sitting in interviews, validations and tests are a real cost, and belong in the document even when nobody invoices them.

    Who signs, and what they sign

    The signature establishes who answers for the starting number, who will decide on the agreed date whether the project continues, and with what authority.

    That same person has to be able to close the project, because if whoever signs lacks that power the stop criteria stay decorative and the initiative runs on inertia until the budget is gone. It happens more often than people admit.

    It is also worth fixing a materiality threshold. Below a certain figure the decision stays with the function head on a short form, above it the full document and the risk assessment go to committee. That rule cuts time spent on small initiatives and protects large ones from hasty approval.

    Where to start

    The method for selecting use cases is in how to choose the first use case and in prioritising AI use cases.

    The decision criteria are described in go/no-go criteria, the six-dimension framework in AI Canvas, and the cost lines in what AI projects really cost and the AI cost nobody budgeted for.

    For classification, which belongs before the calculation, see AI systems risk classification.

    To build the value case for your own use cases you can book an assessment session.

    Frequently asked questions

    What should an AI project value case contain?

    Eight elements: the measured problem with period and source, a baseline of volume and time per unit, the non-AI alternative costed with the same method, the scope of the solution, expected value stated as a range with declared assumptions, three-year total cost, risk classification, and stop criteria with numeric thresholds and a date.

    How do you measure a process baseline before an AI project?

    With three quantities and a period: volume of units handled, time per unit timed on a sample of at least thirty cases by two different people, and the rework rate. The minimum period is four weeks, or two full cycles if the process has monthly peaks, and collection happens before the project is announced.

    How is the expected value of an AI project calculated?

    Volume times time saved per unit times fully loaded hourly cost, then corrected by three declared factors: the share of cases the system covers, residual verification time on the output, and the adoption rate in year one. The result belongs in a range rather than a single number.

    Why does the business case need a non-AI alternative?

    Because without one the comparison is between doing the project and doing nothing. The two cheaper options, process intervention and deterministic rules, have to be costed with the same arithmetic, and the value of AI calculated on the delta against them rather than against the manual starting process.

    What are the most common calculation errors in AI business cases?

    Counting the same freed hours twice across different projects, declaring as a saving capacity that stays in the company without reallocation, ignoring output verification time, using pay rate instead of fully loaded cost, and discounting internal project time to zero.

    Want to discuss this for your company?

    30 minutes with us to figure out where to start, or an AI Rating to measure your starting point.

    #value case#business case#go/no-go#cost#prioritisation